Keep up to date with the progress of North View

We have begun the construction of our new state-of-the-art mental health inpatient unit on the North Manchester General Hospital site. This £105.9 million unit will transform the mental health inpatient experience for our service users, their families and our staff. 

Find monthly updates on site activity below. Read more about the journey so far here.

Progress update - August 2023

Construction has progressed at a pace on site again this month, even though the weather has not been ideal for late summer. As the roofing starts to complete in some sections of the development, the internal walls ceilings and first fix electrical and mechanical works has begun, keeping progress on track.

Progress Update Photo 2 Progress Update Photo 1

The last sections of steel frame superstructure at the main entrance and admin block, at the northern end of site is virtually complete. This milestone will be recognised by the Topping out ceremony arranged for the 21 September, to mark the last piece of steel being fixed in place.

Progress Update Photo 3 Progress Update Photo 4

Metal decking and framing systems, ground floor slab works, intumescent painting of steelwork, steel framing systems, brickwork, windows, curtain walling, roofing and mechanical and electrical works are all continuing to progress from south to north across the site, at varying levels of progress.

 Progress Update Photo 6

High and low voltage infrastructure works continue within the electrical sub-station and the mechanical plantroom is structurally complete. The off-site high voltage point of connection to energise the sub-station on site, is programmed for 5October.

Finally, the Community Skills Centre is planned to open next month (12 September). The hands-on skills centre will support local residents ages 16-24 who are not in employment, education, or training to gain new skills and experience for employment and will help close the future construction skills gap.

 Progress Update Photo 8

The first trade cohort will support 15 trainees and provide the opportunity to gain a Level 1 Award in a construction trade of their choice, alongside basic digital, maths and English skills, a CV, Construction Skills Certification Scheme (CSCS) Card and a minimum of 70 hours practical work experience.

Progress update – July 2023

The construction site has been transformed over the last month, flooded not just by rain but with materials, cranes and labour resource, it quickly has become a very busy site.

Photo of North View Site  Photo of North View Site 2

 

The steel frame superstructure is approximately 75% constructed and it is due to be 100% complete by mid-September. The steel framing system and metal decking is progressing across the volumes from south to north.

North View photo of steel frame  North view photos of steel frame 2

 

The electrical sub-station and mechanical plantroom are now both watertight and electrical switchgear is being installed. The new high voltage electrical supply is due for connection to site in September.

North View Photo electrical substation

 

Windows, curtain walling, roofing, wall insulation and internal partitions are on-going on volume 4 (the first section of construction at the southern end of the site). Internal first fix mechanical and electrical works are due to commence in August, within this volume.

North View photo of building with new windows inserted

A ‘wet trades’ skills school has now been set up on the construction site for the local community, schools, colleges and NHS staff/families, to learn construction skills (plastering, bricklaying etc.). A ‘dry trades and seminar facility is due to open in August/September within an existing building on the existing Park House/North Manchester site.

Progress update – June 2023

Works are progressing at a pace with the steel frame superstructure being constructed from south to north on site. Steelwork to three volumes (ward blocks) has been completed and two others are ongoing.

steel frame 1  steel frame 2

Metal decking has been completed to volume 4 (first ward block) and ground floor slab works, intumescent paint and steel framing system has also commenced to this area.

Metal decking

The electrical substation masonry superstructure and roof is complete, and the transformer is now in-situ. The mechanical plantroom slab is cast and masonry underway.

electrical substation

Pedestrian access along Crescent Drive has now re-opened, following repositioning of site hoarding, the final section of Gabion Wall is underway adjacent to Central Drive.

view of steel frame

To support social value activities during the construction of the North View development, the main contractor (IHP) is participating in many initiatives that hope to enhance the employment, skills, community resilience, health, and wellbeing to those living in the local area.

In late 2024, North View will replace Park House as the in-patient mental health unit on the North Manchester General Hospital site. It has been decided to mark the transition into the new state of the art building, with the burial of a time capsule.

Wording for the time capsule has been agreed and IHP are visiting local schools and community groups in North Manchester to develop the content.

IHP are planning the opening of a skills centre in August, within the Medical Education Building at Park House, to provide construction training, seminars and toolbox talks for local residents, schools, colleges, NHS staff and their families.

Progress update - May 2023

With the continuing dry weather conditions, works are progressing well on site. The steel frame superstructure including the pre-cast concrete staircases to Volume V4 (the ward block on the lower ground level at the southern end) has now been completed.

Steel frame of building  concrete structure of stairs

Pads and foundations for the adjacent (lower and upper) Volumes (V3 and V5) are complete and the steel work for these has commenced. Foundations and drainage to the next (lower and upper) Volumes (V2 and V6) moving north, has also commenced. Notes on Steel Frame: A volume represents a ward area, there are 8 volumes.  Our steel programme sequence starts on V4 followed by V3 then V5, V2, V6, V1 and finishes with V7.

foundation pads for building  drainage for building  builders working on building foundations

The energy centre masonry is progressing well up to roof level and the mechanical plantroom foundations have commenced.

aerial view of the site

The main site cabins, welfare and offices have now fully relocated to the southern end of the site and the tarmac haul road is on-going.

The permanent site boundary hoarding on Crescent Drive is being moved back sequentially, to allow pedestrian access, now that adjacent Gabion Walls have been completed.

site entrace

As part of the social value plan, Integrated Health Projects (IHP) - The Trust’s Principal Supply Chain Partner for North View – along with staff from the North View Project Team, Maple Ward and their service users, recently completed some garden tidying and planting on Maple Ward at Park House on the North Manchester General Hospital site. This was well received and made a difference physically and mentally for all.

 

Photos of garden space photos of staff working on outdoor garden planters photo of garden space after work

 

Ex-England and Everton footballer Trevor Steven visited the IHP construction site on Tuesday 30 May, to provide a talk to their site operatives on mental health in construction. Another visit is planned to capture wider North View stakeholders.

 

Progress update - April 2023

Following some mixed weather conditions for April, building work on North View has continued at pace. This can now be evidenced with the above ground steel super structure works that is visible on site.

Area V4 Erection of structural steelworkArea V4 Erection of structural steelwork

Lower ground floor area V4 steelwork  Lower ground floor area steel frame for North View

Steelwork was delivered to site on the 17 April and a ‘bolt tightening’ event was held on the 25 April, to mark the specific milestone of steelwork erection. You can read more about this here: Steel Frame construction marks major milestone in building of North View, Manchester | News and Events | Greater Manchester Mental Health NHS FT (gmmh.nhs.uk)

Trust Director of Finance and project Senior Responsible Owner, Suzanne Robinsonon site to tighten a ‘golden bolt’ with staff from Park HouseTrust Director of Finance and project Senior Responsible Owner, Suzanne Robinsonon site to tighten a ‘golden bolt’ with staff from Park House

Vibro piling, ground (lime) modification and soft spot remediation works have all been completed within the month. Pad/foundations to the upper and lower levels plus the masonry super structure to the electrical sub-station, has also commenced.

Completion of ground beam designCompletion of ground beam design

HV LV substation facing brickworkHV LV substation facing brickwork

Adjustments to site gate locations for access of steelwork and materials is underway and there are currently approximately 60 site operatives working on site.

Upper ground floor foul drainage manholeUpper ground floor foul drainage manhole

A location beneath the seating/circulation area in the new North View Café Garden has been agreed, to locate the time capsule. Visits to local schools and community groups are on-going to discuss the time capsule content required.

Planning is also underway to accommodate a Skills Centre on site, so the local community, schools and colleges etc. can experience some basic construction skills, under the supervision of IHP Vinci Construction.

North View construction site

Progress update – March 2023

Despite the snow, ice and low temperatures, building work on North View continued. We are working from the South to the North of the site and ground works are well underway with the installation of ground bearing pad foundations to one of the patient wings on the lower level of the site.

Vibro piling, which is the installation of densely compacted columns into soil, has commenced on the upper level of the site and the sub-station foundations/slab and main drainage outfall are now complete. There are currently approximately 55-60 people working on the construction site.

This month, we held open days for the public, staff, and visitors to learn more about our new mental health inpatient unit as part of an Open Doors event. Participants had the opportunity to look around the ‘live’ construction site as part of a site tour, which demonstrated a mixture of planned, in-progress and completed works. During the tour, the team told participants about the project and their roles in the construction process and answered questions. Here’s an update from one of the tours: Greater Manchester Mental Health NHS Foundation Trust on LinkedIn: #gmmhimprovingnorthmcr 

Open days will be repeated further down the construction calendar, as the works progress.

North View building site  

North View building site

North View building site

 North View building site

North View building site  

North View building site

North View building site  

North View building site

 

Progress update – February 2023

Building works are continuing and we are making good progress on site, with the formation of attenuation tanks to store excess rainwater and main drainage outfall. We are continuing with site boundary vacuum excavation work and limescale modification. Backfill to the retaining wall has been completed and gabion walls are 75% complete.

This month, as part of the social value plan, stakeholders from GMMH, DAY Project Management Ltd, and Integrated Health Projects (IHP) - The Trust’s Principal Supply Chain Partner for the new North View building - spent time litter picking in Crumpsall Park and surrounding areas. Positive feedback was received by residents, passers-by and ‘Keep Manchester Tidy’. 27 bags of rubbish were collected. You can read more about this here: Clean up crew around North Manchester hospital site! | News and Events | Greater Manchester Mental Health NHS FT (gmmh.nhs.uk)

Also, within the month, IHP held a ‘Safety Moment Stand Down’ session, a guest speaker provided a very poignant Health and Safety presentation, to compliment a very informative event. Further events will be held as construction progresses.

North View building site  

North View building site - attenuation tank

North View building site

 North View building site

North View building site  

North View building site - gabion walls

Progress update – January 2023

We are making good progress on the new unit. Demolition of all remaining buildings on the site is now complete. We now have full access to the entire site with the final restricted area handed over from Manchester University NHS Foundation Trust to GMMH and Integrated Health Projects, our Principal Supply Chain Partner, in December 2022.

Due to the size and nature of the land, a significant amount of work in the early stages is required to level up the site. New reinforced concrete retaining walls, down the centre of the site, which also form the central access corridor for the new building, will be completed by the end of January 2023. Stone gabion retaining walls being constructed along the Crescent Road site perimeter will support the building's external grounds and gardens.

Over the next 3 months, work will continue across the site, largely below ground as the core building infrastructure is put in place, including the installation of new below ground drainage and utility services that will enable the new development to function.

Other works includes the buildings foundations and the installation of the prefabricated, structural steel frames. This is when the outline of the building will become very much visible!

Watch our construction video to see how the new building will take shape. We are currently around the 20 sec mark.  

Progress update - December 2022

Building works for North View - our new purpose-built development – continues on the North Manchester General Hospital site.

The photos below show the construction of the reinforced concrete structural retaining walls that also form the central access corridor for the new building.

The photo shows the construction of the reinforced concrete structural retaining walls that also form the central access corridor for the new building.

The photo shows the construction of the reinforced concrete structural retaining walls that also form the central access corridor for the new building.

The photo shows the construction of the reinforced concrete structural retaining walls that also form the central access corridor for the new building.

 

The photos below show the stone gabion retaining walls being constructed along the Crescent Road site perimeter that will support the building's external grounds and gardens.

The photo shows the stone gabion retaining walls being constructed along the Crescent Road site perimeter that will support the buildings external grounds and gardens.

The photo shows the stone gabion retaining walls being constructed along the Crescent Road site perimeter that will support the buildings external grounds and gardens.

The photo shows the stone gabion retaining walls being constructed along the Crescent Road site perimeter that will support the buildings external grounds and gardens.

Progress update – November 2022

A ‘ground breaking’ ceremony was held on Thursday 24 November 2022 and invited partners to celebrate and mark the key milestone in the project. Read more here: Ground Breaking marks official start of North View – Manchester’s new £105 million mental health unit | News and Events | Greater Manchester Mental Health NHS FT (gmmh.nhs.uk)

Group of people in protective gear standing in front of a construction digger

 

Piling and concrete pouring takes place to form the foundations for the central spine of North View.  

Photo of concrete pouring taking place at North View site

Concrete pouring takes place

Photo of North View foundations being put in place

Piling to form the foundations of North View

Work is continuing to demolish the remaining site buildings and isolate any ‘live’ site services that were left in-situ. 

Photo of site during demolition removal work

Demolition removal work

 

Progress update – October 2022

Building work continues on site. IHP have been erecting safety fencing to secure the site perimeter and deployed welfare facilities for construction staff. Initial works are underway to level the site off, including removal of old basement structures on the site. ​ 

Bulldozers levelling the North View site

Bulldozers levelling the site 

Progress update – September 2022

We’ve taken possession of the site for our new development alongside our contractor, IHP, to begin the construction of North View. Demolition has concluded by Manchester University NHS Foundation Trust (MFT), and the site has been formally handed over to us. 

Below are start and finish photographs showing the work completed on the site of our new development. 

Image of old Park House building at start of demolition work

Start of demolition & asbestos removal work

Image of old Park House building after demolition has completed

Completion of demolition work

Materials were kept on site for re-use in the foundations and earthworks for North View (stockpile shown above). 

Materials were salvaged for reclamation to minimise impact on landfill. 

North View Hero icon

As a patient

As a service user, relative or carer using our services, sometimes you may need to turn to someone for help, advice, and support. 

Find resources for carers and service users  Contact the Trust